Our weekly PM update

Thanks for taking the time Monday to meet for the pre-drywall meeting. We were able to get the home rewired and the gas line that was cut out replaced.  We have the rough inspections called in and just waiting on the inspector. The drywall was stocked today. Next week we will insulate, get an insulation inspection and should be in drywall mid week.  The siding will be started next week also.