Our weekly PM update
Good week with the slab plumbing installed and passed inspection. The
slab was prepped and we are just waiting for the inspection. Next week
the slab will be poured and framing started. It is very exciting when
the home starts to go up. All of the windows and doors have been
delivered also and will be ready to go in once the walls are set.
No comments: